Friday, October 28, 2011

This project is nearing completion with only punchlist work remaining for project completion.

Wednesday, October 19, 2011

The contractor is scheduled to install sod this week (weather permitting). After sod the only punchlist work remains for project completion.

Friday, October 14, 2011

The contractor is scheduled to install sod early next week. After sod the only punchlist work remains for project completion.

Friday, October 7, 2011

The contractor is scheduled to continue topsoil placement in preparation for sod and asphalt pavement patching/restoration next week.

Friday, September 30, 2011

This week Berger Excavating will be completing the final water main disconnection on Glenview Road. Next week, Berger Excavating is scheduled to continue restoration of driveways and parkways.

Friday, September 23, 2011

This week Berger Excavating will be completing water services on Glenview Road. Next week, Berger Excavating is scheduled to complete water main connections at Glenview Road and Highland Road. Additionally, next week Berger Excavating is scheduled to begin restoration of driveways and parkways.

Friday, September 16, 2011

Next week Berger Excavating will continue transferring the individual water services for each home from the old main to the new main. The morning of the water service work, the contractor will knock on your door to notify you of the pending water shutoff and give you ample time to use your water. The shutoff will last for 1 to 2 hours on average. Once installed, they will ask you to flush your system, and if no one is home, they will use an outside hose bib connection to flush the new service. If you have discolored water, please open your faucets and flush out the lines and the water should clear up.

Friday, September 9, 2011

Next week Berger Excavating will continue transferring the individual water services for each home from the old main to the new main. The morning of the water service work, the contractor will knock on your door to notify you of the pending water shutoff and give you ample time to use your water. The shutoff will last for 1 to 2 hours on average. Once installed, they will ask you to flush your system, and if no one is home, they will use an outside hose bib connection to flush the new service. If you have discolored water, please open your faucets and flush out the lines and the water should clear up.

Friday, September 2, 2011

Next week Berger Excavating will begin transferring the individual water services for each home from the old main to the new main. The morning of the water service work, the contractor will knock on your door to notify you of the pending water shutoff and give you ample time to use your water. The shutoff will last for 1 to 2 hours on average. Once installed, they will ask you to flush your system, and if no one is home, they will use an outside hose bib connection to flush the new service. If you have discolored water, please open your faucets and flush out the lines and the water should clear up.

Friday, August 26, 2011

Berger Excavating will flush the new water main and chlorinate the new water main this week and into next week.

Upon receipt and approval of the testing results (possibly mid- to late next week), Berger Excavating will begin transferring the individual water services for each home from the old main to the new main. The morning of the water service work, the contractor will knock on your door to notify you of the pending water shutoff and give you ample time to use your water. The shutoff will last for 1 to 2 hours on average. Once installed, they will ask you to flush your system, and if no one is home, they will use an outside hose bib connection to flush the new service. If you have discolored water, please open your faucets and flush out the lines and the water should clear up.

Friday, August 19, 2011

Berger Excavating will flush the new water main and chlorinate the new water main next week.

Upon receipt and approval of the testing results, Berger Excavating will begin transferring the individual water services for each home from the old main to the new main. The morning of the water service work, the contractor will knock on your door to notify you of the pending water shutoff and give you ample time to use your water. The shutoff will last for 1 to 2 hours on average. Once installed, they will ask you to flush your system, and if no one is home, they will use an outside hose bib connection to flush the new service. If you have discolored water, please open your faucets and flush out the lines and the water should clear up.

Friday, August 12, 2011

Berger Excavating will pressure test the new water main today and chlorinate the new water main next week.

Friday, August 5, 2011

Berger Excavating will be working on water main connections this week and early next week. Mid- to late next week, Berger Excavating is looking to pressure test and chlorinate the new water main.

Friday, July 29, 2011

Berger Excavating will continue working on the installation of valves, fire hydrants and main connections along Glenview Road (working westbound) this week and into next week. Berger Excavating will also be installing the water main crossings across Glenview Road late this week and early next week.

Friday, July 22, 2011

Berger Excavating will continue working on the installation of valves, fire hydrants and main connections along Glenview Road (working westbound) next week.

Friday, July 15, 2011

Berger Excavating will continue working on the installation of valves, fire hydrants and main connections along Glenview Road (working westbound) next week.

Friday, July 8, 2011

Berger Excavating is scheduled to resume horizontal directional drilling of the water main crossing Glenview Road next week. Berger will also be completing various water main connections and fire hydrant installations.

Thursday, June 30, 2011

Berger Excavating will continue with the horizontal directional drilling of the water main along the south side of Glenview Road into next week.

Friday, June 24, 2011

Berger Excavating will continue with the horizontal directional drilling of the water main along the south side of Glenview Road into next week.

Thursday, June 16, 2011

Berger Excavating will continue with the horizontal directional drilling of the water main along the south side of Glenview Road into next week.